Multifunctional Centre of Boucherville - thumbnail 1Multifunctional Centre of Boucherville - thumbnail 2Multifunctional Centre of Boucherville - thumbnail 3

Multifunctional Centre of Boucherville

CIVIL ENGINEERING
Turnkey project, integrated into the long range plan of the municipality, where the superficial drainage is collected in sewer pipes and redirected into ditches, towards a permanent pond. This parking has 193 places with a dock leveller drained towards a trench in the building. The design was elaborated by respecting the recommendations of a performance specification while optimizing the costs of construction.

No water retention was required for this project and even the surface of the roof is drained in a pipe emptying into a ditch.

Client:
Pomerleau

Architects:
Lemay Associés / Architecture, Design

Completion: 2001